Quantcast
Viewing all articles
Browse latest Browse all 54

18 months and 3 panels later, Balganga dam still stalled

MUMBAI: The Balganga dam project in Pen taluka, planned to supply 350 million litres of water daily (MLD) to Navi Mumbai, has been stalled for the past 18 months because of huge cost variations. The City & Industrial Development Corporation (Cidco), which is funding the project, cannot decide the final cost of this crucial project after the contractor demanded the cost be raised two-and-a-half times. Since last year Cidco has appointed three panels to probe if the contractor's demand was justified or not. But experts on the different panels arrived at varying...

Viewing all articles
Browse latest Browse all 54

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>